March 31, 2014 energyair Share this post Construction of the HVAC system is progressing at Cypress Creek High School in Orlando. The team set all three of the 500-ton chillers on Saturday, March 29, just minutes before intense storms hit. We started the remodel of Building 300 on March 1 and started construction of Building 1200 (a new, two-story building) on March 24. We are on schedule to have the CEP and these two buildings completed for the start of school in August. For more information on this project’s HVAC scope of work, see post from 12/19/13.